News

Luxury hotel with complex constraints

Text Tim JanssensImage AB-Eiffage, Fjord RED

Luxury hotel with complex constraints

170 high-end suites, a reception area, rooftop restaurant and skylounge at a height of 26 metres, fitness, wellness and meeting rooms: the Mövenpick Brussels Airport hotel in Zaventem offers its guests everything their hearts desire, starting this autumn. With its prominent location, breathtaking 360° views and unique 'curtain walls' - in both glass and concrete - the stately complex has some valuable assets. Although a lot of expertise was needed in the shell construction phase to connect the dots.

AB-Eiffage pulled up the wind- and watertight structural shell from the foundation slab.

Mövenpick Brussels Airport rose on the edge of the ageing Keiberg business park, right next to the Brussels Ring Road. The luxury hotel by property developer Fjord RED, operated under franchise by the French Accor Group, is one of the first exponents of a promising (re)development with work, accommodation and leisure facilities. The playful design, which sprung from the creative quiver of Buro Architectuur, is a nod to Belgian surrealism. The architectural eye-catchers are the transparent upper floor that houses the reception, the rooftop restaurant and the sky lounge, and the façades in architectural concrete, in the form of austere white panels that were equipped with integrated folds in specific places. These wavy ornaments symbolise flapping curtains. On the end facades, the ornate 'façade curtains' are more than 20 metres high, making the building immediately eye-catching. 

On the longitudinal facades, the façade panels in white architectural precast concrete are mounted in band form, including elements with integrated 'curtain structure' between the window openings.
Mövenpick Brussels Airport's playful design is a nod to Belgian surrealism.

Phased implementation

The new hotel will be realised in three phases. Of phases 1 and 2 - i.e. the elongated wing parallel to the Brussels Ring Road and the short intermediate volume, which together form an L - the structural work is almost complete. Of phase 3 - the second elongated wing, which will be inserted at right angles to the other - only the ground floor has been built for the time being. It was AB-Eiffage that pulled this off. 

"We started work after the execution of the earthworks and the installation of a soilmix wall, which the client himself undertook," explains project manager Bart Reyniers. "We started from the foundation slab and erected the wind- and watertight shell, which consists of a three-storey underground car park (including some technical premises on level -1), the superstructure of the first and second phases (ground floor + eight floors) and the glazed plinth of the third phase."

The concrete cladding is an eye-catcher in itself.

Concrete in all shapes and sizes

The structural shell of Mövenpick Brussels Airport consists mainly of concrete: walls poured on site, columns, precast walls, hollow and solid walls ... "As the height of the building increased, we evolved from walls poured on site to hollow and solid precast walls in function of the execution speed," explains Bart Reyniers. "In addition, we also realised some masonry walls, but this was rather limited. As soon as the supporting structure was ready, we started installing the façade panels in white architectural precast concrete, supplied by Enjoy Concrete. On the longitudinal facades, these were mounted in band form - including elements with integrated 'curtain structure' between the window openings - while the end facades featured large panels up to 5 metres high and weighing 9 tonnes. The latter were transported upright via exceptional transport so that we could hang them in place using a single tower crane."

It involves five to six different roof levels. "It was a feat to get that puzzle fully boxed together," stresses Bart Reyniers.

Puzzle at roof level

The biggest challenge, however, was the construction of the roof level, Bart Reyniers points out. "The realisation of the lower and upper levels was pretty straightforward, but that changed as soon as we reached the eighth floor. There, things suddenly became a lot more complex, as the hotel is located right under one of Brussels Airport's approach routes. There were therefore strict restrictions on the maximum building height. To reconcile these with accessibility requirements, there are all kinds of lowered zones in the roof surface, resulting in five to six different roof levels. It was a juggling act to get that puzzle completely put together. We also had to take into account the connection to phase 3, even though no final plans or models of this existed yet. We therefore had to rely on textual info only. This had the necessary implications for, among other things, the alignment of the curtain walls on the upper floor and the façade panels in architectural precast concrete. Fortunately, the rapport with the builder and architect was excellent, so we could always go to them with questions and comments. We are finalising the last things these days and the interior finishing is also in full swing, so the hotel is well on track for opening this autumn!"    

Question about this story? Ask your question

In this story

  1. BuilderFjord RED (Bruges)
  2. ArchitectBuro Architectuur (Merchtem, Opwijk)
  3. Main contractor(s)AB-Eiffage (Antwerp)
  4. Study office stabilityCOBE engineers (Bruges)

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectNews
Share this article

Advertisement

Follow on Hotelvak Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.